News from the construction site

Progress is being made on the Energy Center, Central Logistics and Campus

Join us for a glimpse behind the scenes at the Energy Center and Central Logistics. We will also show you an important large component that was delivered on July 14.

Energy Center

This is what the energy center looks like – the new buffer tanks can be seen on the left.

Construction is now beginning on the interior fittings of the Energy Center. Most of the plant technology is already on site, for example new buffer storage tanks (pictured on the left) that are considerably larger than all previous models at the location. We can also see the heating and cooling distributors which distribute the capacities at our site. Connecting the new media to the existing buildings requires numerous construction measures. “We are making good progress on connecting existing buildings,” says Project Manager David Eichhorn. The media line, i.e. the connection to the existing buildings, should be finished by September.

An important room: the low-voltage main distribution board

Pictured is the energy center's new low-voltage main distribution board. It is the central component for power distribution.

Campus

What looks like an elongated swimming pool on the north side of the company grounds is actually an overflow canal. The basin for this structure was delivered in the early morning hours on July, 14 and installed using a crane. This acts like a large cistern, to put it simply. We will need this in the future because considerably more rain water will be collected by the new buildings than before. The overflow canal first collects this water and then passes it on to the drainage system in a controlled manner.

To ensure that existing wastewater lines can be extended and adjusted, the tower parking lot also had to make room.

And the topsoil in the new campus area is currently being excavated, straightened and improved. A calcareous mixture is being added to the subsoil to ensure the future stability of the buildings.

Central Logistics

At first, the heat wave and rain posed obstacles to the activities: But in early July, the ground slab for the new shuttle storage system was cast. On the slab, a small machine that looks like an automatic lawnmower is taking measurements for the steel structure. This will be constructed starting in late July.

On the pre-dispatch building, the columns and roof trusses have already been put into place. Preparatory work is currently underway on the intermediate level, which will accommodate workstations for order picking in the future.